Anthropic's prospectus confirms on-site gas power at some planned data centers, but gives no fuel mix
An estimate that hit the Hacker News front page Sunday says 87% of Anthropic's power will come from gas in 2028. The company's IPO filing doesn't give a number, but it does describe gas-fired sites, uncapped fuel costs and a $500 million power-contract guarantee.
By Morgan Laning · Published

An estimate that hit the Hacker News front page Sunday says 87% of Anthropic's power will come from gas in 2028. The company's IPO filing doesn't give a number, but it does describe gas-fired sites, uncapped fuel costs and a $500 million power-contract guarantee.